Client:
ISTHA
Project Type:
Transportation - Phase I Study , Phase II Design
Construction Cost:
$62,750,000
ISTHA I-355 Veterans Memorial Tollway
Spring Creek to 151st Street in Will County, IL
Project Description
HOH was responsible for Phase I Study and Phase II Design for paving and fine grading improvements for mainline and crossroad for the Veterans Memorial Tollway (I-355) from Spring Creek to 151st Street in Will County, IL. Contract I-05-7709. Construction Budget - $62,750,000.
Scope of Work
- This 6.5 mile project included mainline pavement of three lanes in each direction of the mainline I-355, full diamond - interchange with IL Route 7 including ramps and signalized intersections, construction of cross road box culverts, - detention basins and erosion control of cleared and graded areas. 
- The improvement included reconstruction of one half mile of IL Rte 7, to a six lane section leading to the new bridge - over I-355 complete with two thru lanes in each direction and left and right turn lanes. 
- The new mainline pavement included a full length median barrier and full shoulders on the left and right including a - gutter along the right edge of shoulder. 
- Traffic signals for the ramp intersections and the intersection with Gougar Road as well as full interchange lighting - were provided. 
- The Phase I Study included a PDR, LDS, IDS’s, BCR’s, Barrier Warrant Analyses, and Traffic Management Analyses, and - multiple Public Hearings. 
 
                         
            
            
          
              